Good Practice.
I have a number of rules worth following.
-
Use good quality, cohesive concrete.
-
Deliver it to within 1250mm of the bottom of where you are placing that concrete.
-
Vibrate it properly. In, out slowly, every 200mm.
-
Do not have to lift the poker more than 2m to move it along. That probably restricts formwork height to 2m each pour.
-
Do not loosen or remove the formwork for 3 days.
If your project has enough labour and a supervisor to watch these 5 rules are applied, no concrete ought to visibly leak.
|
|
|
|